GA-EPD cites Suwannee Riverkeeper and US EPA against TPM titanium mine near Okefenokee Swamp 2019-09-12

GA-EPD told USACE the mining application is incomplete, asked for comments to be reopened, and cited Suwannee Riverkeeper and Georgia River Network:

“Understanding that groundwater hydrologic effects associated with the Twin Pines project have been a central concern expressed by federal resource/regulatory agencies, NGOs (e.g. the Suwannee Riverkeeper and Georgia River Network), and the public at large, we respectfully submit that the 404/401 permit application as submitted thus far is not complete since it lacks full information and findings regarding hydrogeologic factors on site and post-project effects to hydrogeology/groundwater. We feel that it is inappropriate and premature to close the project comment window when such notable elements of the environmental documentation for this project have not yet been made available. documentation which we at GaEPD judge to be important to our review of this project.”

[the 404/401 permit application as submitted thus far is not complete]
the 404/401 permit application as submitted thus far is not complete

This was revealed by USACE in a Public Notice of September 17, 2019. So far, this is the only update posted by the Corps since it closed comments on September 12, 2019.

It also includes comments by U.S. EPA, also saying the application is incomplete, and also cited by GA-EPD. EPA cites cumulative effects and notes numerous lacking documents and studies. EPA concludes:

“Due to the potential for the proposed Twin Pines Minerals mine to adversely affect the hydrology of the Okefenokee NWR, the EPA believes that there is the potential for this project as proposed to cause adverse effects to water quality and the life stages of aquatic life or other wildlife dependent on aquatic systems. The EPA finds that this project, as proposed, may result in substantial and unacceptable impacts to aquatic resources of national importance, as covered in Part IV. paragraph 3(a) of the August 1992 Memorandum of Agreement between the EPA and the Department of the Army regarding CWA Section 404(q).”

Apparently USACE is at least listening to the public and the public and NGOs such as Suwannee Riverkeeper.

You can still send in comments. The Corps won’t say they will read them, but they explicitly won’t say they won’t read them, so keep sending them in, and publish them on social media, as op-eds, etc.

GA EPD

See also separate PDF.

From: [redacted]
To: Ross, Holly A CIV USARMY CESAS (US)
Cc: [redacted]
Subject: [Non-DoD Source] GaEPD Comments, Request for Comment Extension for SAS-2018-00554, Twin Pines Mineral Mine, Charlton Co.
Date: Thursday, September 12, 2019 6:23:19 PM


To:
U.S. Army Corps of Engineers, Savannah District
Attn: Ms. Holly Ross
1104 North Westover Blvd., Suite 9
Albany, GA, 31707
Holly.a.ross@usace.army.mil <mailto:Holly.a.ross@usace.army.mil>

Dear Ms. Ross,

Since the July 12, 2019 Joint Public Notice for the subject Twin Pines Mineral Mine project. the GaEPD Wetlands Unit has reviewed the massive 404/401 application documents provided thus far by project environmental consultant TTL. has attended a July 25, 2019 information session and site visit organized by the U.S. Fish & Wildlife Service/Okefenokee National Wildlife Refuge, has attended an August 13, 2019 public meeting in Folkston, GA as hosted by consultant TTL and applicant Twin Pines Mineral, LLC, has had in-house discussions and briefings here at GaEPD, and has received project comments notably received as of today from the U.S. Environmental Protection Agency, the Georgia River Network and the Suwannee Riverkeeper.

At this time we wish to observe that notable elements of the environmental documentation for this substantive project have not yet been prepared, completed and distributed to us at GAEPD. Appendix F of the 404/401 permit application cites that a series of reports addressing hydrogeologic factors at the Twin Pines site will be completed in the future, but have not yet been completed. Particularly notable among these reports is the ‘“Groundwater Models of the Twin Pines Project Area, Trail Ridge, Georgia” — This report will document the groundwater models produced to evaluate the pre-mining conditions, the impact of mining activities on groundwater flow, and the post-mining groundwater conditions.”’ Understanding that groundwater hydrologic effects associated with the Twin Pines project have been a central concern expressed by federal resource/regulatory agencies, NGOs (e.g. the Suwannee Riverkeeper and Georgia River Network), and the public at large, we respectfully submit that the 404/401 permit application as submitted thus far is not complete since it lacks full information and findings regarding hydrogeologic factors on site and post-project effects to hydrogeology/groundwater. We feel that it is inappropriate and premature to close the project comment window when such notable elements of the environmental documentation for this project have not yet been made available. documentation which we at GaEPD judge to be important to our review of this project.

Thank you for your consideration of this matter.

[redacted].PWS
Manager – Wetlands Unit
Georgia Environmental Protection Division
7 Martin Luther King, Jr. Drive, Suite 450
Atlanta, GA 30334
[redacted]
[redacted]

US EPA

See also separate PDF.

[The mine and the swamp]
The mine and the swamp
PDF

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION 4
ATLANTA FEDERAL CENTER
61 FORSYTH STREET
ATLANTA, GEORGIA 30303-8960
SEP 1 2 2019

Colonel Daniel H. Hibner
District Engineer
Attn: Ms. Holly Ross
U.S. Army Corps of Engineers
100 W. Oglethorpe Avenue
Savannah, Georgia 31401-3640

Subject: SAS-2018-00554, Twin Pines Minerals LLC heavy mineral sands mine in Charlton County, Georgia

Dear Colonel Hibner:

The U.S. Environmental Protection Agency has reviewed the Joint Public Notice SAS-2018-00554 announcing a Clean Water Act (CWA) Section 404 permit application submitted by Twin Pines Minerals, LLC to mine heavy mineral sands on a 2.414-acre property near St. George, Georgia in Charlton County. After issuing the initial public notice on July 12, 2019, the U.S. Army Corps of Engineers, Savannah District (Corps) issued a second public notice on July 19, 2019, that included the complete permit application and extended the comment period to September 12, 2019.

Twin Pines Minerals, LLC anticipates its heavy mineral sands mine will be 12,000 acres mined in approximately 1,000-acre parcels over 30 years. The public notice describes the proposed work in Charlton County as Phase-1. The PN indicates that the discharge of dredged or fill materials associated with the Phase-1 project as proposed would directly impact 587 acres of wetlands and 7,112 linear feet of streams.

The western boundary of the 12,000-acre total mine area abuts the Okefenokee National Wildlife Refuge (NWR), which is managed by the U.S. Fish and Wildlife Service (U.S. FWS). The Okefenokee NWR was established in 1937 and encompasses over 90 percent of the 438.000-acre Okefenokee Swamp. According to the U.S. FWS, the Okefenokee Swamp includes eight different habitat types: shrub swamp, mixed cypress forest, prairies, pure cypress forest. swamp islands, blackgum forest and bay forest. Within the Okefenokee NWR itself, 233 species of birds (including three federal endangered species) have been identified, as well as 49 species of mammals, 64 species of reptiles, 37 species of amphibians and 39 species of fish.

The Okefenokee NWR is the largest NWR in the eastern United States, and over 350.000 acres of the Okefenokee NWR is National Wilderness Area. It is one of fewer than 600 National Natural Landmarks designated by the U.S. Secretary of the Interior nationwide, is designated a Wetland of International Importance per the Ramsar Convention and has been placed on the U.S. World Heritage Tentative List, which means it may be nominated for consideration as a World Heritage Site. The EPA considers the Okefenokee NWR an Aquatic Resource of National Importance.

[Documents missing: Wetlands, discharges, hydrogeology]
Documents missing: Wetlands, discharges, hydrogeology

The 2,414-acre Phase-1 project area lies as close as 1.7 miles from the border of the Okefenokee NWR, and the proposed mining footprint within Phase-1 will lie as close as 2.7 miles from the NWR (measured via georeferenced aerial photography). The depth of mining across the Phase-1 project area will vary from approximately 25 feet below land surface in the west to an average of 50 feet below land surface in the central and eastern mine area. The Phase-1 project mining will include excavation of the geologic formation known as Trail Ridge. The U.S. Geological Survey has described Trail Ridge as impounding the Okefenokee Swamp,1 and the U.S. FWS has referred to Trail Ridge as a “geomorphological ‘dam’ on the east side of the swamp maintaining the hydrology of the swamp.”2 The effects of mining through Trail Ridge on local and regional groundwater levels in and affecting the NWR are uncertain at this time.

The applicant proposes to replace 522 acres of wetlands and 2.454 linear feet of streams during mine reclamation. However, detailed wetland and stream reclamation / restoration plans have not been provided. The EPA recommends that additional detailed information be provided on the reclamation / restoration plans for our review in order to evaluate the feasibility of restoring the underlying soil and hydrologic conditions that presently support existing wetlands and streams in the Phase-1 project area and thereby ensure that all impacts to waters of the United States are appropriately avoided, minimized and compensated for, consistent with the CWA 404(b)(1) Guidelines.

Regulations at 40 CFR Section 230.10(c) prohibit discharges that will cause or contribute to significant degradation of waters of the United States, and 40 CFR Section 230.11 requirements include the consideration of secondary and cumulative impacts from proposed discharges. Based on the limited available information, the applicant has not demonstrated that the proposed project will not result in significant degradation, including individual or cumulative effects to fish and wildlife; ecosystem diversity, productivity and stability; and recreational, aesthetic and economic values. Excavation and reclamation of the proposed mine area may alter local or regional groundwater hydrology. Changes in water table elevations and the rate and direction of shallow ground water movement as a result of mining and reclamation may alter hydrologic conditions in the Okefenokee NWR. Regulations at 40 CFR Section 230.40 specifically state the permitting authority should consider potential impacts to sanctuaries and refuges designated under State and Federal laws or local ordinances when making the factual determinations under 40 CFR Section 230.11 and the findings of compliance or non-compliance with the restrictions on discharge at 40 CFR Section 230.12.

1 Force, E.R. and F.J. Rich. 1989. Geologic evolution of Trail Ridge eolian heavy-mineral sand and underlying peat, northern Florida. U.S. Geological Survey Professional Paper 1499. Washington, D.C.

2 Letter from Donald W. Imm, U.S. Fish and Wildlife Service, to Colonel Daniel Hibner, U.S. Army Corps of Engineers, Savannah District. February 20, 2019.

Appendix F of the permit application introduces hydrogeologic investigations undertaken or in the process of being completed on and adjacent to the proposed mine area. However, no technical information pertaining to any of these efforts is included. The need to evaluate cumulative effects of the proposed project are particularly relevant considering the applicant has expressed the intent to mine up to an additional 9.600 acres north of Phase-1. The EPA requests that the applicant provide a detailed analysis of the potential individual, cumulative and secondary effects set forth in 40 CFR Sections 230.10(c) and 230.11, including but not limited to hydrologic effects on the NWR, pursuant to 40 CFR Section 230.40, and the St. Marys River.

[this project, as proposed, may result in substantial and unacceptable impacts to aquatic resources of national importance]
this project, as proposed, may result in substantial and unacceptable impacts to aquatic resources of national importance

Due to the potential for the proposed Twin Pines Minerals mine to adversely affect the hydrology of the Okefenokee NWR, the EPA believes that there is the potential for this project as proposed to cause adverse effects to water quality and the life stages of aquatic life or other wildlife dependent on aquatic systems. The EPA finds that this project, as proposed, may result in substantial and unacceptable impacts to aquatic resources of national importance, as covered in Part IV. paragraph 3(a) of the August 1992 Memorandum of Agreement between the EPA and the Department of the Army regarding CWA Section 404(q).

Thank you for the opportunity to review the permit application submitted by Twin Pines Minerals, LLC. We look forward to working with your staff and the permit applicant. If you have any questions, please do not hesitate to contact me at [redacted] or have a member of your staff contact at [redacted].

Sincerely,
[redacted]
[redacted] Director
Water Division

cc: [redacted] U.S. Fish and Wildlife Service
[redacted] Georgia Environmental Protection Division

US National Marine Fisheries Service

See also separate PDF.

While these U.S. NMFS comments were somewhat noncommital, they are pretty clear that they do not support the mining application, and that further inquiries should be sent.

[This position is neither supportive of nor in opposition to authorization of the proposed work.]
This position is neither supportive of nor in opposition to authorization of the proposed work.
PDF

USACE Cover letter

See the Public Notice on USACE’s website, and the PDF on the WWALS website.

[SAS-2018-00554-Charlton-0917-SP-HAR-0001]
SAS-2018-00554-Charlton-0917-SP-HAR-0001

See also separate PDF made by WWALS.

Thanks to WWALS Science Committee Chair Dr. Tom Potter for important parts of the Suwannee Riverkeeper comments to USACE.

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can join this fun and work by becoming a WWALS member today!

One thought on “GA-EPD cites Suwannee Riverkeeper and US EPA against TPM titanium mine near Okefenokee Swamp 2019-09-12

  1. James Files

    Thanks to the folks who got off their butts and worked to slow this down. Hopefully the effects of their efforts will be apparent a long time from now.